Blue Mountains Courier Herald
Grier Creek bridge schedule set up
Date: Apr 11, 2008
Email Story
Print
Report Typo

Grey County officials hope to start construction on the new Grier Creek bridge by early June, according to a timeline announced last week.

Grey Director of Transportation and Public Safety Gary Shaw said the county plans to call tenders by April 25, closing on May 16.

If there's an accepted bid it will go to the Transportation and Public Safety Committie on May 22 and, if approved there, to County Council for ratification June 3. That would set up a construction start for June 9, Shaw said.

User Comments
Most Recent Stories

McGuinty still refusing to share gas-tax revenues with small municipalities: ...
Although a billion dollars is a lot of money, it needs to be put in perspective given the need is much, much greater. [more]


New trail opens
The new looping trails have been in the works for over a decade ... [more]

Historical society meets at Grey Roots
Dressed in period costumes, the attendants ... [more]



Privacy Policy - Copyright ©1996-2007 Metroland Media Group Ltd.
SIMCOE.COM is an online publication serving the communities of Barrie, Alliston, Collingwood/Wasaga Beach, Midland, Stayner and Orillia in central Ontario, Canada. All rights reserved. Reproduction, modification, distribution, transmission or republication of any material from simcoe.com is strictly prohibited without prior written permission from MMetroland Media Group Ltd.
Metroland
Metroland North Media
Torstar Digital